Use Of Form Work Design And Construction Of High Building

Use Of Form Work Design And Construction Of High Building
Abstract
This research project is designed to critically assess the use of formwork design and construction of high rise building. The researcher has carried out an extensive research on how important well designed and constructed formwork could be in the construction of high rise building in Nigeria. The researcher in order to achieve this aim visited libraries, handouts, journals and distributed questionnaires, personal observations. The data obtained from questionnaire was presented and analyzed using the percentage method. The hypothesis was tested using chi-square statistical formula. The researcher found out the followings; that contractors of these days no longer go for superior and construction most contractors prefer using block where concrete should have been used. Recommendations were made as follows it is recommended that contractors should learn the proper way of constructing formwork for concrete components. Standard materials should be used for every formwork construction. There should be a stipulated standard for formwork construction in construction site in Nigeria.
Table Of Contents
Preliminary Page(s)
- Title page
- Approval page
- Dedication
- Acknowledgement
- Abstract
- Table of contents
Chapter One
1.0 Introduction
- 1.1 Background of the study
- 1.2 Statement of the problem
- 1.3 Objectives of the study
- 1.4 Scope of the study
- 1.5 Significant of the study
- 1.6 Definition of terms
Chapter Two
2.0 Literature Review
- 2.1 Formwork and Concrete for types
- 2.2 Slab Formwork (Deck formwork)
- 2.3 Flexible Formwork
- 2.4 Formwork Elements
- 2.5 Characteristics of a good Formwork
- 2.6 Materials for Formwork
- 2.7 Types of Formwork
- 2.8 Order and method of Removing Formwork
- 2.9 Preventing Formwork Failures
- 2.10 Control Measures Erecting Formwork
Chapter Three
3.0 Research Design/Methodology
- 3.1 Introduction
- 3.2 Research Design
- 3.3 Sources/Method of Data Collection
- 3.3.1 Primary Source
- 3.3.2 Secondary Source
- 3.4 Population and Sample Size
- 3.5 Sample Technique
- 3.6 Validity and Reliability of Instrument
- 3.7 Method of Data Analysis
Chapter Four
4.0 Presentation and Analysis of Data
- 4.1 Introduction
- 4.2 Presentation of Data
- 4.3 Analysis of Data
- 4.4 Test of Hypothesis
Chapter Five
5.0 Conclusion and Recommendation
- 5.1 Conclusion
- 5.2 Recommendations
- References
- Appendix I
- Appendix II
Chapter One
1.0 Introduction
1.1 Background Of The Study
Form work is the term given to either temporary or permanent mould into which concrete or similar materials are poured. In the context of concrete construction, the false work supports the shuttering moulds.
Formwork are hollow moulds, which serve as a form for concrete in this way, building components of concrete and reinforced concrete as site concrete will be constructed. In the precasf plant, mostly formwork elements come into use. The use of form work comply with the highest requirements and enable an exact, efficient and thereby economical construction of pre-cast concrete parts.
Some of the earliest examples of concrete slabs were build by Roman Engineers because concrete is quite strong in resisting compressire loads, but has relatively poor tensile or torsional strength, these early structure consisted of arches, vanlts and domes. The most notable concrete structure from this period is the panthern in Rome. To mould this structure, temporary scaffolding and formwork or false work was build in the future shape of the structure. These building techniques were not isolated to pouring concrete but were and are widely used in masonry because of the complexity and limited production capacity of the building material, concretes rise as a favored building materials did not occur until the invention of Portland cement (and developments by the edision Portland Cement Company) and Reinforced concrete.
1.2 Statement Of Problems
Despite the numerous achievements of formwork in the construction of high rise buildings, a lot of problems are still associated with the design and construction of formwork for building production. These problems among others are:
- Most construction companies do not see the need to the quality material for formwork hence they are discarded after use in most cases. This has constituted a lot of problems design and construction of formwork.
- Use of inexperienced contractors is another problem confronting effective design and construction of various types of formwork for high rise building.
- It is observed that in most construction companies, all the processes involved in formwork construction for concrete components are not duely observed by the contractors and this in most occasion causes formwork failure in high rise building.
- In most cases, the owner of the project detects to the contractor the type of material to use for him or her and this has affected so many formworks design and construction negatively.
1.3 Objective Of The Study
The main objective of this research work is to access the design and construction of various types of formwork for construction of high rise building. The specific objectives of this research work are as follows:
- To determine the effectiveness of quality materials in the design and construction of quality formwork for high rise building.
- To evaluate the experience of indigenous contractors in formwork design and construction
- To determine the various processes involved in formwork design and construction.
- To determine the problems associated with effective design and construction of formwork for high rise buildings.
- To suggest solution on how to remedy the problems associated with effective design and construction of formwork for high rise buildings.
1.4 Research Question
For the purpose of this research work, the following research questions were formulated.
- What are the effective of quality materials in the design and construction of quality formwork for high rise buildings?
- What are the level of experience of the indigenous contractors in formwork design and construction?
- What are the various processing involved in formwork design and construction of formwork for high rise buildings?
- What are the problems associated with the effective design and construction of formwork for high rise buildings?
- What could you suggest as the means of minizing the problems associated with effective design and construction of formwork for high rise buildings?
1.5 Significance Of The Study
This research work will benefit so many people and they are:
The Contractor
The contractor will benefit immensely from this work, as the work will expose them to the various types of formwork, the processes involved in formwork construction and so many other experiences they will gain from the work.
The Students
The study would be significant to students who might wish to use it as a basis for further research, it will serve as a spring board from which further research might take off. The data already gathered and documented in this project will serve as a source of information to student as well serve as a reference material in their classroom work.
1.6 Definition Of Terms
Formwork:
Formwork is an ancillary construction, used as a mould for a structure into this mould, fresh concrete is placed only to harden subsequently.
Construction:
Is the process of preparing for and forming buildings and building systems or it is simply an act of making something especially building bridges etc.
Assessment:
The process of documenting knowledge, skills, attitudes, and beliefs.
Concrete:
Is a composite material composed mainly of water, Aggregate and cement.
Contractor:
This is an organization or individual that contracts with another organization or individual (the owner) for the construction of a building, road or other facility.
Chapter Five
5.0 Conclusion And Recommendations
5.1 Conclusion
The design and construction of formwork for concrete component cannot be overemphasized in the construction industry. Its importance is very significance in construction site.
Some of the earliest example of concrete slab were built by Roman Engineers because concrete is quite strong in resisting compressive loads, but has relatively tensile or torsional strength, these early structure consisted of arches, vaults and domes. The most notable concrete structure from this period is the pantheon Rome. To mould this structure, temporary scaffolding and formwork or false work was built in the future shape of the structure. These buildings techniques were not isolated to pouring concrete but were and are widely used in masonry because of the complexity and limited production capacity of the building material, concretes rise as a favored building material did not occur until the invention of Portland cement ( and development by the Edison Portland cement company) and reinforced concrete.
Basically, a formwork from the formwork system or the formwork lining and the formwork support exists which formwork and which formwork element to use depends on the type as well as the function of the component. A formwork depicts the negative element of finished concrete part and design through the choice of formwork lining the visible surface of the concrete pieces so that the high pressure which accure by the dumping of the concrete can be intercepted, formwork must be compact, fit exactly, clean and stable prefabricated shuttering (concrete shuttering) elements comply with these guidelines especially well and guarantee constant high quality results.
Formwork can be made out of timber, plywood, steel, precast concrete or fibre glass used separately or in combination. Steel forms are used in situation where large numbers of re-use of the same forms are anticipated. For small works, timber formwork proves useful. Fibre glass made of precast concrete and aluminum are used in cast-in-situconstruction such as slabs or members involving curved surfaces.
5.2 Recommendations
The following recommendations were made based on the research findings:
- It is recommended that contractors should learn the proper way of constructing formwork for concrete components
- Standard materials should be used for every formwork construction.
- There should be a stipulated standard for formwork construction in construction sites in Nigeria.
- There should be a penalty for those contractors who use sub-standard materials for construction of formwork.
- Accurate measurements should be employed while constructing the formwork.


The Complete Material Will Be Sent to You in Just 2 Steps
Quick & Simple…
![]()
Make Payment (Through Transfer) of ₦5,000 to the Account Below
![]() | Acc No: 0811003731 |
| Samphina Academy | |
| Current Account |
Or CLICK HERE To Pay With Debit Card
| FOR STUDENTS OUTSIDE NIGERIA | |
| CLICK HERE To Pay With Card ($15) | |
| FOR GHANA STUDENTS (GHS 100) | |
![]() | MTN MoMo |
| 0553978005 | |
| Douglas Osabutey | |
![]()
Send the Following Details on WhatsApp ( 07062590260 ) After Payment
- Payment Details
- TOPIC: Use Of Form Work Design And Construction Of High Building
The Complete Material Will Be Sent To You On WhatsApp After Receiving Your Details
T & C Apply
Students Review
List of Related Works
Impact Of Poor Maintenance Of Government Hospitals In Edo North Senatorial District
Assessment Of The Cause, Prevention And Repairs Of Cracks In Building
Assessment Of Ergonomic Adaptability Practices Among Selected Construction Craftsmen
Strength Development In Concrete Using Different Type Of Cement
Radiation Shielding Materials Using Different Types Of Concrete
Exploring The Influence Of Workplace Trust Over Health Workers Performance
Design Of A Standard And Functioning Primary Health Care (PHC)
Paradigm For Total Quality Management In Building Maintenance Operation
Sustainable Building Materials For Reduced Environmental Impact On Project In Lagos State
Building Collapse In Schools Nigeria; Causes, Effects And Solutions
An Appraisal Of The Effects Of Delay On Construction In Nigeria
Issues And Challenge In The Execution Of Public Sector Housing Projects In Nigeria
Impact Of Maintenance Of Buildings And Infrastructural Facilities To The National Economy
An Investigation Into The Safety Culture In Building Construction Industry
Delay On Construction Project Delivery In Nigeria: Effect, Causes And Solutions
Assessment Of Materials Management Strategies On Project Cost In Lagos State
The Challenges Of Indigenous Building Construction Firms In Nigeria
Comparative Of Construction Processes Of Innovative And Conventional Building
Comparative Assessment Of The Strengths Of Solid And Glued Laminated Timber
Causes And Remedies Of Poor Maintenance Of Public Building
Quality Control As An Effective Tool For Efficient Project Delivery (A Case Study Of Imo State)
A Critical Review Of The Causes Of Cost Overrun In Construction Industries In Developing Countries
Maintenance Of Building – A Case Study Of Affin Kaduna
Comparison Of Demolished Concrete Waste And Glasses As Materials For Concrete Construction
Sustainable Building Materials And Effective Project Delivery In Kwara State Construction Company
Roles Of Recycled Materials In Sustainable Building Construction
Project Planning And Programming As Tools For Effective Project Delivery
Factors Influencing Craft-men Productivity In Africa
Improving Urban Residents Awareness Of The Impact Of Household Activities On Climate Change
A Comparative Study Of The Entrepreneurial Characteristics Of Architecture And Building Students
Importance Of Incentives And Motivation Of Human Element In Construction Industry
Green Building As Innovation In Nigeria Construction Industry
Investigating Into The Issue Confronting Women Participation In Building Construction Industry
Analysis Of Factors Influencing Material Wastage On Building Site In Nigeria
Assessment Of Factors Affecting Maintenance Service Of Specialist Work In Nigeria
Strategies For Controlling Cracks In Residential Buildings
Risk Management And Value Engineering: Mitigating Challenges In Construction In Nigeria
Labour Productivity Analysis Using Multi-Variable Linear Regression Technique
Assessing Material Management Practices On Construction Site In Nigeria (A Case Study Of Ado Ekiti)
Labour Control In Building Industry
Assessment Of The Training Needs Of Craft Skill Workers In North-Western Nigeria
Exploring The Sustainability Of Using Aluminum Materials For Durable Doors And Windows In Building
An Evaluation Of Financial Incentives In Private Organization In Nigeria
Wage Determination In The Public Sector Industrial And Labour
Effectiveness Of Non-Financial Motivational Schemes On Construction Workers Output In Nigeria
Effluent Impact On Water Quality (A Case Study Of Aba River In Aba North L.G.A. Of Abia State)


