The Effect Of Timely Delivery Of Construction Projects On The Economic Development Of Nigeria

The Effect Of Timely Delivery Of Construction Projects On The Economic Development Of Nigeria
Abstract
Timely delivery of construction projects can fasten up drastic development in any country. Construction delay has become endemic in Nigeria, it is imperative to create awareness of the extent to which delays can adversely affect project delivery. This study identifies, by questionnaire evaluates and through empirical method assesses the effects of construction delays. The findings showed that time and cost overruns were frequent effects of delay. Delay had significant effect on completion cost and time of 61 building projects studied. Client-related delay is significant in Nigeria. Acceleration of site activities coupled with improved clients’ project management procedure and inclusion of appropriate contingency allowance in pre-contract estimate should assuage the adverse effect of construction delays.
Chapter One
Introduction
1.1 Background of the Study
Time impacts are inevitable on construction projects, primarily because of the uniqueness of each project and the limited resources of time and money that can be spent on planning, executing and delivering the project.
Time factors are inherent in all of project construction’s undertakings. Construction projects have long been recognized as particularly cost, time and risk-laden. Some of the time and cost factors associated with the construction process are fairly predictable or identifiable; others may be totally unforeseen. The constructed project may not perform as anticipated because the owner may have unrealistic expectations regarding the delivery time of construction forcing contractors into unrealistic gambles, corner-cutting or commitments that may not be realistic (Frimpong 2003).
Project success can be defined as meeting goals and objectives as prescribed in the project plan. A successful project means that the project has accomplished its technical performance, maintained its schedule, and remained within budgetary costs. Project management tools and techniques play an important role in the effective management of a project. Therefore, a good project management lies in the management tools and techniques used to manage the project. Project management involves managing the resources workers, machines, money, materials and methods used. Some projects are effectively and efficiently managed while others are mismanaged, incurring much delay and cost overruns and negatively affecting the economy (Frimpong 2003).
Assessing construction projects’ delivery time is critical in today’s market-driven economy.
To improve the economy and maximize long-term return on this public investment, government agencies have recently started utilizing new types of contracting methods that are designed to achieve multiple project objectives, including minimizing construction cost and duration, while maximizing its quality.
In recent years, many departments of transportation, in various states have started to apply new highway contracting methods, including: Bidding on time i.e., to encourage competition among contractors to minimize project duration (Holt et al 2000), Incentive/ disincentive contract clauses that provide financial incentives to reduce construction duration, Night time construction that seeks to cut service disruption and project time by requiring contractors to work during off-peak night time hours, Warranty contracting that attempts to improve construction quality by making contractors liable for the performance of the facility after project completion.
These new and emerging contracts place an increasing pressure on decision makers in the construction industry to search for an optimal/near-optimal resource utilization plan that minimizes construction time while maximizing its quality. This creates new and pressing needs for advanced resource utilization models that are capable of optimizing the multiple and conflicting objectives of construction time, cost, and quality.
Significant research advancements have been made in the area of optimizing construction resource utilization. This led to a number of optimization models. These models can be classified according to their optimization objectives into models that attempted to:
- Minimize project time and/or improve resource utilization;
- Minimize time and cost for non-repetitive construction using time-cost trade-off analysis
- Minimize time and/or cost for repetitive construction
While the above research study seeks to provide significant contributions to the area of optimizing construction resource utilization, there has been little or no reported research focusing on multi objective models for optimizing construction time, cost, and quality.
1.2 Problem Statement
Misallocation and misperception of time factor in construction projects have resulted in the government of Nigeria paying more than necessary for many projects. Improper time assessment can also cause additional costs in the form of delays which result in poor utilization, increasing social and economic costs.
- Are contractors using the most appropriate resources to execute projects in Nigeria?
- Do they mobilize the needed resources within the approved time frame allotted to their contracts?
- What effects do short time periods and/ or extended time periods have on their project costs?
- Are there remedies to these situations?
These are some of the situations that have prompted the researcher to go deep into the assessment of the cost and time impacts of public sector construction projects in Nigeria.
1.3 Objectives of the Study
The study had the main objective of assessing the effects of timely delivery of construction projects on the economy of Nigeria, but specifically it had the following objectives.
- To establish the extent to which time factors have impacted on construction of projects in the public sector in Nigeria.
- To find out the change in the perception of contractors on time effects on public sector construction in Nigeria.
- To find out the relationship between timely delivery of construction projects and the economic development of Nigeria.
1.4 Research Questions
In order to achieve the objectives of the study, the following research questions were used by the researcher:
- What effects do time factors have on construction of projects in Nigeria?
- Has the perception of contractors on time factors in projects construction changed in recent years?
- What relationship exists between timely delivery of construction projects and economic development in Nigeria?
1.5 Research Hypothesis
- H0: there is no significant relationship between timely delivery of construction projects and economic development of Nigeria.
H1: there is a significant relationship between timely delivery of construction projects and economic development of Nigeria. - H0: there is no significant relationship between timely delivery of construction projects and economic development in Nigeria.
H2: there is a significant relationship between timely delivery of construction projects and economic development in Nigeria
1.6 Significance of the Study
There are several valuable benefits expected by implementing this study. All construction contracts allocate time between owners and contractors. Hence the significance of this study would better inform improved project relationships and communications and enhance construction administration practices between owners and contractors. The significance of establishing the issues related to the construction project delays was to provide a greater insight and understanding on the causes of delays particularly among the main project players: contractors, client and consultants. This can be achieved by applying theoretical concepts discussed in many literatures into practice in real projects. It is hoped that these findings will guide efforts to improve the performance of the construction industry and will be useful to the construction players. Therefore, these findings might encourage the practitioner to focus on delay problem that might have existed in their present or future projects. Other than that, this study is expected to provide a better ways and methods in delivering construction projects by minimize the major causes of delays. The findings would also enhance and broaden time of wide range of risks that could materialize during the design, and construction phases of a project which would subsequently result in better and more prudent designs specifications.
1.7 Scope and Limitations of the Study
The researcher will limit the study to the effects of timely delivery of construction projects on the economy of Nigeria, using the Fly over 2 project constructed by Julius Berger in Uyo, Akwa Ibom State as a case study. Findings and recommendations by the researcher may not be used for general analysis as the researcher could not assess numerous construction projects due to time and financial constraints. Construction of projects in the public sector has assumed significant functions, hence the need for assessment on the cost and time impacts of construction of projects in order to achieve overall project objectives. Historical project schedule and duration data is treated as confidential by Julius Berger Nigeria Plc hence getting data for this study was very difficult. Data collection and analysis was therefore limited to the data received from project supervisors in the field of project construction.
Therefore this project was constrained by the following factors:
Financial Constraints
Bearing in mind the economic state of the nation, it was found difficult in making both ends meet, because of the exorbitant nature of things nowadays in travelling for the collection of data needed for the project.
Time Constraints
Looking at the interval between the resumption and vacation of the final semester for the project to be completed, the time given seemed to be short for the collection of required information for better work to be done.
Non-Availability of Material
During this project, it was noticed that the required materials needed for the project are not documented. Those that were documented lacked access to the storage facilities where they can be reached.
1.8 Definition of Terms
Project Delays:
Construction delays in residential and light construction are often the result of miscommunication between contractors, subcontractors, and property owners. These types of misunderstandings and unrealistic expectations are usually avoided through the use of detailed critical path schedules, which specify the work, and timetable to be used, but most importantly, the logical sequence of events which must occur for a project to be complete.
Timely Delivery:
A timely event happens at a moment when it is useful, effective, or relevant.
Projects:
In project management a project consists of a temporary endeavor undertaken to create a unique product, service or result. Another definition is: a management environment that is created for the purpose of delivering one or more business products according to a specified business case.
Economic Development:
From a policy perspective, economic development can be defined as efforts that seek to improve the economic well-being and quality of life for a community by creating and/or retaining jobs and supporting or growing incomes and the tax base. Overview.
1.9 Organization of the Study
This research work is organized in five chapters, for easy understanding, as follows
- Chapter one is concern with the introduction, which consist of the (overview, of the study), statement of problem, objectives of the study, research question, significance or the study, research methodology, definition of terms and historical background of the study.
- Chapter two highlight the theoretical framework on which the study is based, thus the review of related literature.
- Chapter three deals on the research design and methodology adopted in the study.
- Chapter four concentrate on the data collection and analysis and presentation of finding.
- Chapter five gives summary, conclusion, and recommendations made of the study.
Chapter Five
Summary Conclusion and Recommendation
5.1 Introduction
It is pertinent to note that this research was aimed at cross examining the impacts of delivering construction projects on time to economic developments in Nigeria, thus the topic “the effect of timely delivery of construction projects on the economic development of Nigeria”.
In the preceding chapter, the relevant data collected for this study were presented, critically analyzed and appropriate interpretation given. In this chapter, certain recommendations made which in the opinion of the researcher will be of benefits in addressing the challenges associated with timely delivery of construction projects in Nigeria.
5.2 Summary
There are more than ten factors that causes projects construction delay in Nigeria from the perception of the indigenous and multinational firms are cash flow problems, shortage of construction materials, clients financial difficulties, inadequate consultant experience, incompetent project team, inadequate contractor experience, poor design and delays in design, lack of communication and coordination, an incomplete drawing / detail design and project financing problems. The effects of delay in the industry cannot be overemphasis. The study result confirms the findings of Aibinu and Jagboro (2002) and Murali and Yau (2007) that indicates time overrun, dispute among construction parties, and cost overrun, litigation/arbitration and project abandonment as construction delay effects.
In Akwa Ibom State, Nigeria, most project abandonment experienced were basically due to financial issues from client (individual, corporate and Government), death of the owner, change of government or policy and administrative-related issues (corporate and government).
The results of this study also shows that both the indigenous and multinational firms are subject to construction delay in almost the same pattern, but the effects of delay experience by the two firms type’s differs.
5.3 Conclusion
In conclusion, factors that induce delay on construction projects, however in this study are limited to 15 factors causing delay and they were ranked according to the mean index score. The factors includes: lack of funds to finance the project to completion, changes in drawings, lack of effective communication among the parties involved , lack of adequate information from consultants, slow decision making and contractor’s insolvency, variations. Also, project management problem, mistake and discrepancies in contract document, equipment availability and failure, mistakes during construction, bad weather, fluctuation in prices of building materials, inappropriate overall organizational structure linking to the project and labour strike. Analysis was also carried out on the effect of delay on the project work. Time overrun, increase in final cost of project, wastage and under-utilization of man-power and resources, tying down of client capital due to non-completion of the project, dispute among parties involved were ranked highest. Time is factor that is very essential in all activities that has to be carried out, in the contract document a specific time phase is given for delivery of project and if the time is being exceeded more money is often spent which could lead to increase in final cost of project and also wastage and under-utilization of man-power and resources. The client’s capital has to be withheld due to non-completion of the project which could result into dispute, litigation and arbitration among the workers and management. Also delay can lead to reduced profit for builder and abandonment of building project by the client.
5.4 Recommendations
From the findings of this study the following recommendations were suggested;
- Clients should select contractors with sufficient experience, technical capability and man-power for their projects, and not base their selection on lowest bid considerations only
- Clients should not interfere frequently during the project execution so as to reduce the changes to requirements.
- Clients should pay progress payment to contractors on time as delay in payment impairs the contractor’s ability to carry out work.
- Consultants, while drawing the contract between client and contractor, should include items such as duration of contract, mechanism to resolve disputes and mechanisms to assess the causes of delay.
- Consultants should prepare, review and approve drawings and design documents on time because any delay caused by the consultant engineer in checking, reviewing and approving the design submittals prior to construction phase, could delay progress of work.
- Consultants should monitor the work closely by making inspections at appropriate times and be flexible in evaluating contractor works.
- Contractors should not take up a project in which they do not have sufficient expertise.
- Contractors should engage competent site-managers for smooth execution of work.
- Contractors should plan their work properly and make the entire schedule available.
- Contractors should provide enough equipment to execute their work and also have a maintenance plan for their equipment to prevent frequent breakdowns.


The Complete Material Will Be Sent to You in Just 2 Steps
Quick & Simple…
![]()
Make Payment (Through Transfer) of ₦5,000 to the Account Below
![]() | Acc No: 0811003731 |
| Samphina Academy | |
| Current Account |
Or CLICK HERE To Pay With Debit Card
| FOR STUDENTS OUTSIDE NIGERIA | |
| CLICK HERE To Pay With Card ($15) | |
| FOR GHANA STUDENTS (GHS 100) | |
![]() | MTN MoMo |
| 0553978005 | |
| Douglas Osabutey | |
![]()
Send the Following Details on WhatsApp ( 07062590260 ) After Payment
- Payment Details
- TOPIC: The Effect Of Timely Delivery Of Construction Projects On The Economic Development Of Nigeria
The Complete Material Will Be Sent To You On WhatsApp After Receiving Your Details
T & C Apply
Students Review
List of Related Works
Impact Of Naira Devaluation On The Manufacturing Industry: A Case Study Of Dangote Sugar Refinery
Financial And Economic Performance Of Nigeria
Sustainable Industrial Growth And Economic Development In Nigeria (1990 -2015)
The Impact Of Inflation In Nigeria Economic Development
Examination Of The Grounds On Cbn’s Reservation Against The Circulation Of Cryptocurrency In Nigeria
Effects Of FDI And Exchange Rate Fluctuations On Economic Growth In Nigeria
The Impact Of Youth Unemployment And Economic Development In Nigeria From 1980-2022
Poverty Alleviation And Economic Development In Nigeria (A Case Of Nkwere Local Government)
Effect Of Unemployment On Economic Growth In Nigeria
The Impact Of Fuel Subsidy Removal On Poverty In Nigeria
The Impact Of Mortgage Banking In Nigerians Economic Development Programmes
Maritime Entrepreneurship And Economic Development In Nigeria
Assessing The Significance Of The Tourism Industry On Economic Development Of Nigeria
Historical Background Of The Nigeria Stock Exchange In The Economic Development Of Nigerian
Determinant Of Survival Of Cottage Business In Ekiti State
Human Capital Development And Poverty Level In Nigeria From (1986 To 2023)
Impacts Of Economic Hardship On The Academic Performance Of Students In Auchi Polytechnic, Auchi
The Effect Of Corruption On Sustainable Economic Development In Goodluck Jonathan Regime
The Influence Of Economic Growth On Insurance Market Size
Contribution Of Cashew To The Economy Of Kwara State (1990–2024)
The Role Of African Development Bank In Nigeria Economic Development
Effect Of Unemployment On The Economic Development Of Nigeria
The Effects Of Bank Fraud In The Nigerian Economic Development (21st Century Experience)
The Impact Of Tax Reform On Economic Growth In Nigeria
The Role Of Rural Women Farmers In Economic Development
Role Of Local Government In Economic Development Of Nigeria
The Role Of Insurance Companies In The Economic Development Of Ghana
Modeling Uncertainties In Compressed Natural Gas (CNG) As A Vehicular Fuel In Developing Economies
The Role Of Mass Media In Economic Development In Nigeria
Export Financing In Nigeria: Problems And Prospects
The Effect Of Migrants Remittances On House Hold Welfare And Economic Development
Impacts Of Effective Financing Of Small Business Enterprises On National Economic Development
Development Banks And Their Impact In Economic Development Of A Nation (Extended Essay)
Corruption And Economic Development
The Regional Cooperation And Economic Development Of ECOWAS Member States
A Critical Analysis Of The Impact Of Insurance Industry Towards Economic Development Of Nigeria
The Growth Of Capital Market In Nigeria And The Unfolding Economic Development Of The Nation
Corruption And Economic Growth In Nigeria (1999–2023)
An Assessment Of Globalization And Economic Development In Nigeria
The Role Of Small And Medium Enterprises In The Economic Development
The Impact Of Small Scale Industries On Economic Development Of Nigeria
Effect Of Tax Evasion And Tax Avoidance On Economic Development
Study Of Freight Rate Fluctuations On Global Trade (2010–2020)
Impact Of Insurance Business On The Economic Development Of Nigeria
Accounting For Peace And Economic Development In Nigeria, The North East Case
Impact Of Remittances On Economic Growth In Nigeria (1990 – 2021)