An Appraisal Of Factors Militating Against The Effective Implementation Of Formal Risk Management Techniques In Project Delivery

An Appraisal Of Factors Militating Against The Effective Implementation Of Formal Risk Management Techniques In Project Delivery
Abstract
Non utilization of Formal Risk Management Techniques in project delivery by the project team has been identified as one the causes of project failure This prompts the question ‘what factors are responsible?’ This study therefore first presents Risk management in project delivery as it relates to an integrated project team as well as internal issues. It then focuses on formal Risk management techniques and their processes of implementation with a view to revealing the internal and external barriers that inhibit their utilization in project delivery in Abuja Metropolis, Nigeria. A total of 391 questionnaires were distributed to construction firms and stakeholders in ABUJA metropolis but a total of 203 firms responded.
Data retrieved were analyzed using descriptive statistics, ANOVA and spearman correlation coefficients. The internal barriers were found to be cost and time intensiveness, argumentative sessions that create riskier stance including subjective judgment that lacks accurate results while the external barriers were found to be lack of risk assessment training in place, lack of collaboration by parties on a project, low level of risk consciousness, ineffective monitoring by heads of firms and lack of historical data across the project team’s spectrum. The study recommends strategies such as improving the grey areas in the implementation processes through research for internal barriers and conducting sensitization, legislation, business regulations and mandatory training to overcome the external barriers.
Chapter One
Introduction
1.1 Background to the Study
Despite its numerous challenges, it is the Construction Industry that shapes the development parameters of any nation (Zeiss, 2007). So a firm grasp of the nature and effects of key issues affecting the Industry is always the beginning of developmental wisdom.
The construction industry is bedeviled with global climate change, aging infrastructure, shrinking workforce, declining productivity and information island (Akintoye and Macleod, 1997; El-sayeh, 2008; Smith, 1999 Zeiss, 2007; Hillson, 2002; Wang et al., 2004). Gandu and Musa-Haddary (2007) in their work mentioned high risks and uncertainties as additions to these problems.
In Nigeria, in particular, experts on management studies have lamented the complete neglect of formal risks management principles in the management of most construction projects (Akintoye and Macleod, 1997; Smith, 1999; Kartam and Kartam, 2001; Aina and wahab, 2011). Why most firms opt for the use of informal principle to the detriment of the formal and most beneficial ones is a puzzle that requires an organized study. In an assessment of some special challenges facing the Nigerian construction industry, Odonkor (2011) ranked poor risk understanding and management as the most unappreciated. The nature of this risk challenges as Odonkor (2011) partly observed lies in the failure to employ formal Risks Management Techniques available.
Risk management is fundamental to accomplish those objectives, not only trying to keep away from bad results caused by some special events or uncertain conditions, but also acting as a guide in order to maximize the positive results. Risk Management refers to the culture, processes, and structures that are directed toward effective management of risks –including potential opportunities and threats to project objectives. Although risk is widely studied, it still lacks a clear and shared concept definition: risk is often only perceived as an unwanted, unfavorable consequence. Such a definition embodies two misleading concepts: first, among professionals there is an established consensus that risk needs to be viewed as having both negative and positive consequences. Second, risk is not only related to events, i.e. single points of action, but risk also relates to future project conditions. Conditions may turn out to be favorable or unfavorable. The point is that future project conditions are hard to predict in the early stages of the project life-cycle. In addition, conditions can change during the project lifecycle and the risk is that the conditions are different, and potentially more severe than was first estimated. Risks analyzed only as certain events are further criticized for not taking the degree of impact into consideration. Risks are seldom on-off-types, meaning that risks do not either happen or “not-happen”, the impact of the risk varies greatly, depending on the conditions at the time of the possible occurrence (Finnerty, Floricel and Miller, in Klemetti 2006). Variability and the level of predictability (uncertainty) of the future scenarios determine the quality of risk analysis done today.
Managing risks in construction projects have been recognized as a very important process in order to achieve project objectives in terms of time, cost, quality, safety and environmental sustainability (Mills, 2001). Project risk management is an iterative process: the process is beneficial when is implemented in a systematic manner throughout the lifecycle of a construction project, from the planning stage to completion.
Risk management has become an integral process in managing construction projects. Construction project activities are to be well calculated in-order for the deliverable to be of great use and benefit to its stakeholders. To complete most construction projects on time, minimizing cost and wastages proper risk management techniques must be employed (Tchankova, 2002). According to Mills (2001), systematic risk management is expecting the unexpected or in other words it is a tool which helps control risks in construction projects and its objective is to introduce a simple, practical method of identifying, assessing, monitoring and managing risk in an informed and structured way.
Normally, in risk management process, the first steps will involves risk identification process which includes the prioritization process in order to identify and rank the risk based on its impact and seriousness. Risk that will have a greater impact on a project normally will be handled first and low impact risk will be handled later.
Construction project team consist of professional such as the architect, engineer, and the quantity surveyor that will help to assist and advice the client in order to meet all the project objectives in term of time, quality and cost. Awareness and knowledge on risk management is very crucial so that they will deal with the risk properly which will directly leads to project success. Due to this scenario, this research aims to identify the level of awareness of construction professional specifically Nigerian quantity surveyors towards risk management. Apart from that, it will also aim to identify how risk management being implemented in the Nigerian construction industry and also the potential barrier and challengers in the implementation of risk management specifically from the quantity surveyor’s point of view.
1.2 Statement of the Problem
Embarking on a construction project involves taking risks, as the Nigerian construction industry is not risk-free. No matter how small or simple is the project it is still can go wrong as soon as the two parties, the employer and the contractor signed a contract they have taken onboard the risk (Sawczuk, 1996). The individual in the construction industries that undertake various activities are heterogeneous since client, consultant and contractors have different roles and objectives (flanagan, 1995). Risk management in Nigerian construction industry is actually not widely being practiced.
According to Burchett (2009), Risk in construction, however cannot be eliminated, but it can be minimized, transferred or retained. However, the industry has a very poor reputation for managing risk, with many projects failing to meet deadlines and cost argents (Mills, 2001). In practice, normally in order to deal with the unexpected event, there will be an allocation about 10 percent from the estimated cost of the proposed construction project as a contingency sum. Earlier observation shows that the risk management process is not widely being implemented in Nigerian construction industry. For this reason, this research seeks to identify the barriers and challenges for the implementation of risk management in the Nigerian construction industry.
1.3 Objective of the Study
The main objective of this study is an appraisal of factors militating against the effective implementation of formal risk management techniques in project delivery. Specifically, this study aims to
- Determine the internal barriers that militating against the effective implementation of formal risk management techniques in project delivery.
- Determine the external barriers that militating against the effective implementation of formal risk management techniques in project delivery.
- To proffer solution to the factors militating against the effective implementation of formal risk management techniques in project delivery.
1.4 Research question
- What are the internal barriers militating against the effective implementation of formal risk management techniques in project delivery?
- What are the external barriers militating against the effective implementation of formal risk management techniques in project delivery?
- What are the solutions to the factors militating against the effective implementation of formal risk management techniques in project delivery?
1.5 Significance of the Study
Findings of this study will aid Nigerian quantity surveyors in appreciating the importance of adopting proper risk management techniques in their daily jobs. Since risk management is not widely being adopted in Nigerian construction industry, this research will help to promote the practice of risk management among the industry’s players.
In addition to this, being an inter-discipline type of research, both the consultants and contractors and also the industry as a whole may benefit from the outcome of the research and have better understanding on risk management.
1.6 Scope and Limitation of Study
This research study will focus on risk management practices adopted by construction firms and stakeholders in Abuja metropolis, Nigeria. All findings and recommendations from the study are limited to findings and recommendations based on the chosen sample size.
In carrying out this study, the researcher was faced with time and finance constraints, as lectures did not give room for more time to extend the research time frame. Finance on the other hand made printing, transportation to cover a wider area difficult.
1.7 Definition of Terms
Risk
This is the potential of losing something of value, weighed against the potential to gain something of value.
Risk Perception
Risk perception is the subjective judgment people make about the severity of a risk, and may vary person to person
Practice
Is the act of rehearsing a behavior over and over, or engaging in an activity again and again, for the purpose of improving or mastering it, as in the phrase “practice makes perfect
Quantity Surveyor
A Quantity Surveyor (QS) is a professional working within the construction industry concerned with construction costs and contracts.
Construction
In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect.
Risk Management
Is the identification, assessment, and prioritization of risks followed by coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of unfortunate events or to maximize the realization of opportunities.
Chapter Five
Conclusion and Recommendation
5.1 Conclusion
In this study, our focus was to carryout an appraisal of factors militating against the effective implementation of formal risk management techniques in project delivery. The study specifically was aimed at determining the internal barriers that militating against the effective implementation of formal risk management techniques in project delivery, determining the external barriers that militating against the effective implementation of formal risk management techniques in project delivery and proffering solutions to the factors militating against the effective implementation of formal risk management techniques in project delivery.
The study adopted the survey research design and randomly enrolled participants in the study. A total of 203 responses were validated from the enrolled participants where all respondent are active workers in the 5 selected construction firms and stakeholders in Abuja metropolis .
The findings revealed that The internal barriers were found to be cost and time intensiveness, argumentative sessions that create riskier stance including subjective judgment that lacks accurate results while the external barriers were found to be lack of risk assessment training in place, lack of collaboration by parties on a project, low level of risk consciousness, ineffective monitoring by heads of firms and lack of historical data across the project team’s spectrum.
5.2 Recommendation
The study recommends strategies such as improving the grey areas in the implementation processes through research for internal barriers and conducting sensitization, legislation, business regulations and mandatory training to overcome the external barriers.


The Complete Material Will Be Sent to You in Just 2 Steps
Quick & Simple…
![]()
Make Payment (Through Transfer) of ₦5,000 to the Account Below
![]() | Acc No: 0811003731 |
| Samphina Academy | |
| Current Account |
Or CLICK HERE To Pay With Debit Card
| FOR STUDENTS OUTSIDE NIGERIA | |
| CLICK HERE To Pay With Card ($15) | |
| FOR GHANA STUDENTS (GHS 100) | |
![]() | MTN MoMo |
| 0553978005 | |
| Douglas Osabutey | |
![]()
Send the Following Details on WhatsApp ( 07062590260 ) After Payment
- Payment Details
- TOPIC: An Appraisal Of Factors Militating Against The Effective Implementation Of Formal Risk Management Techniques In Project Delivery
The Complete Material Will Be Sent To You On WhatsApp After Receiving Your Details
T & C Apply
Students Review
List of Related Works
Delay On Construction Project Delivery In Nigeria: Effect, Causes And Solutions
Impact Of Effective Building Production Management In Successful Building Project Delivery
Appraisal Of The Impact Of Delays In Project Delivery In Construction Industry
The Impact Of Budgeting And Budgetary Control In Construction Project Delivery In Nigeria
Impact Of Material Management On Project Delivery And Productivity Of An Organization
The Study Of The Various Incentive Scheme That Increase Productivity And Project Delivery
Sustainable Building Materials And Effective Project Delivery In Kwara State Construction Company
The Effect Of Fluctuations And Variations In Construction Project Delivery
Assessment Of The Impact Of Poor Communication On Construction Project Delivery
Assessment Of Materials Management Strategies On Project Cost In Lagos State
Quality Control As An Effective Tool For Efficient Project Delivery (A Case Study Of Imo State)
Factors Affecting The Competence And Project Delivery Of Small Indigenous Construction Firms
Plant Resource Control As An Effective Tool To Project Delivery In Building Industry
Project Planning And Programming As Tools For Effective Project Delivery
Contributions Of Insurance In The Management Of Risk In Nigeria Oil Industries
Insurance Industry And Risk Management In Nigeria
The Impact Of Disaster Risk Management On The Development Of Small Scale Business
Impact Of Credit Risk Management On Liquidity, Growth And Profitability Of Commercial Banks
Analyzing The Role Of Risk Management In A Textile Production Company
Risk Management Strategies And Film Growth Among Listed Deposit Money Banks In Nigeria
Risk Management In Nigerian Banks: A Case Study Of Union Bank Uyo
The Impact Of Corporate Governance And Risk Management On Bank Performance
The Role Of Internal Control In Risk Management
Risk Management; Means Of Minimizing Accident In The Aviation Industry In Nigeria
Effect Of Cost And Risk Management On The Use Of Automobile Method To Manual Method Of Construction
Risk Management And Value Engineering: Mitigating Challenges In Construction In Nigeria
Risk Management And Portfolio Analysis In The Capital Market
Examining Corporate Social Responsibility As A Risk Management Strategy
Credit Risk Management And Deposit Money Bank Performance In Nigeria
The Effect Of Corporate Risks Disclosure On Market Value Of Money Deposit Bank In Nigeria
Credit Risk Management And Banks Profitability In Nigeria
Risk Management In Building Construction
Financial Risk Management In Nigeria
The Effect Of Risk Management On Business Performance
Business Risk Management And Organizational Stability In Golden Penny Foods Ltd
Credit Analysis And Loan Management In The Banking Industry
Risk Management As An Efficient Means Of Achieving Corporate Objectives
Credit Risk Management And Banking Sector Performance In Nigeria